Guangyuan Democratic League Candlelight Junior High School Sports Field Renovation Project

Guangyuan Democratic League Candlelight Junior High School Sports Field Renovation Project

Update Time:2025/4/2 17:51:57
Guangyuan Democratic League Candlelight Junior High School Sports Field Renovation Project
Guangyuan Democratic League Candlelight Junior High School Sports Field Renovation Project
Project Background
Silicon PU courts, known for their superior cushioning and eco-friendly properties, are widely used for basketball, badminton, tennis, and other ball sports. This project aims to construct standardized sports facilities with high-performance silicon PU materials, ensuring safety, comfort, and durability for both competitive training and public fitness.
Technical Specifications
1. Material Structure
(1)Base Layer: Concrete or asphalt foundation (flatness ≤3mm/3m)
(2)Elastic Layer: 6mm silicon PU cushioning (impact attenuation ≥30%)
(3)Surface Layer: 2mm anti-slip wear-resistant coating (wet slip resistance ≥0.5)
2. Key Performance
(1)Shock Absorption: 2.5-5mm vertical deformation, reducing joint injury risks
(2)All-Weather Durability: Operational range -30℃ to 120℃, UV-resistant
(3)Eco-Certification: Complies with GB/T 19851.11-2005 & EU EN 14904, VOC ≤50g/L
Project Benefits
1. Social Value: Increases venue utilization by 300%+, supporting school/community sports events
2. Cost Efficiency: 8-10 year lifespan with 40% lower maintenance vs acrylic courts
3. Rapid Construction: 15-25 days (depending on site conditions), compatible with old court renovation
Implementation Process
Phase
Scope
Duration
Basic treatment
Grinding, cleaning, and repairing of the base surface
5-7 days
Material laying
elastic layer+surface layer layered coating
8-12 days
Maintenance and acceptance
curing (≥ 72h)+performance testing
2-6 days
project information
Project Name: Guangyuan Democratic League Candlelight Junior High School Sports Field Renovation Project
Project timeline: August 2023
Partner: Education Bureau of Zhaohua District, Guangyuan City
Project content and construction area:
8mm silicon PU basketball court 4780 ㎡
Acceptance results: Test verification confirms the silicone PU court surpasses GB/T 22517.6-2020 requirements with shock absorption (65%±3%), vertical deformation (1.5-2.5mm), and slip resistance (BPN≥80). The client has signed off on environmental compliance (TVOC<0.3mg/m³, heavy metals ND) and flatness (≤1.5mm under 3m straightedge), with particular commendation for its all-weather durability and athlete injury prevention performance.

Are you looking for a reliable manufacturer of down home textile products?

We can quickly provide customers with market analysis, technical support and customized services.
Please send your message to us
*Email
*Name
*Tel
*Title
*Content
Upload
  • Only supports .rar/.zip/.jpg/.png/.gif/.doc/.xls/.pdf, maximum 20MB.
Address